Twelve stages
to your first order.

Stages overlap and the ranges assume no unusual obstacle. Anything that depends on an authority, a landlord or a utility company is marked, because those timelines are not ours.

01

Feasibility, city & cuisine

Weeks 1–2

Which city, which delivery zone, which cuisines are underserved there, and whether the numbers work at achievable order volumes. Platform coverage and competition mapped before anything else.

Note. Delivery is hyper-local. A cuisine that is saturated in one postcode can be absent three miles away. This is done at postcode level, not city level.

02

Entity formation

Weeks 2–4

LLC or Corporation in the United States, private limited company in the United Kingdom, with registered agent or office, tax identifiers and constitutional documents.

Note. The company holds the lease or licence, the equipment, the staff contracts and the liability. Food businesses attract liability that should not sit in your personal name.

03

Menu & brand design

Weeks 3–6

The brand set designed around a single shared prep list, with dishes chosen for margin, consistency in a delivery box, and hold time. Names, identity, photography plan and packaging specification.

Note. This stage determines the equipment, so it happens before the kitchen is specified. Designing the kitchen first and the menu afterwards is the most expensive mistake available here.

04

Site search & the four checks

Weeks 4–10

Commissary bays or shell units identified, then each tested against permits and use class, the extraction route, utility capacity, and access and lease terms.

Note. All four must clear. More sites are rejected on the extraction route than on rent, and we would rather lose a site than take one that cannot legally do the job.

05

Permits & registration

Weeks 6–14

Health department permit or food business registration, planning or zoning confirmation, waste and grease trade agreements, and the food safety management documentation the authority expects.

Note. These are physical processes ending in an inspection. Timelines are the authority's, not ours, and no one can guarantee the outcome.

06

Equipment specification & procurement

Weeks 7–13

The cooking line, refrigeration, prep, sinks, warewashing, interceptor, holding and packing station specified against the menu and procured, new or used as appropriate.

Note. Specified after the menu and before the fit-out, so the utilities can be sized to the actual load rather than to a guess.

07

Fit-out & installation

Weeks 9–18

Extraction and fire suppression, utility connections and upgrades, drainage and interceptor, then equipment installation, commissioning and gas and electrical certification.

Note. In a commissary bay this is a fraction of the work. In a shell it is the longest and riskiest stage, and the one most likely to slip.

08

Recruitment & food safety

Weeks 12–17

Head chef or kitchen manager first, then line cooks. Contracts, right-to-work checks, payroll registration, food handler certification, and appointment of the named person responsible for food safety.

Note. The head chef is the most important hire in the venture and the single largest operational risk. We start this early and we hire a deputy from the outset.

09

Suppliers & procurement

Weeks 13–17

Food suppliers, packaging, cleaning chemicals, linen and waste contracts negotiated, with a second source identified for every critical line.

Note. Packaging is not an afterthought. It determines whether food survives the journey, and it is a permanent per-order cost that is worth negotiating properly.

10

Platform onboarding

Weeks 14–18

Each brand registered on each delivery platform, menus built, photography shot, descriptions written, pricing set, delivery zones configured, and the order aggregator connected.

Note. Photography drives conversion more than almost anything else on a listing. It is the line in the budget we will argue hardest against cutting.

11

Documentation & procedures

Weeks 15–19

Recipes and specifications, prep lists, opening and closing checks, temperature and waste logs, allergen matrix, cleaning schedule, incident procedure and the compliance calendar — all handed over in editable form.

Note. Recipes documented properly are what stop the business living inside one chef's head. You own every document at handover.

12

Soft launch & stabilisation

Weeks 17–22

One brand live first at limited hours to test ticket times and packaging, then the remaining brands added. Thirty days of close monitoring, then transition to the standing platform desk.

Note. Launching all four brands at once into an untested kitchen produces long ticket times and early one-star reviews, which are extremely hard to recover from.

Who does what

Coordination is not the same as authority.

We are a setup and operations firm. We are not a law firm, an accountancy practice, an environmental health authority or a food safety auditor. This table is the boundary and it is in every agreement we sign.

ActivityAkontec Licensed / localYou
City, cuisine and brand setResearches and recommends —Decides
Company formationPrepares and coordinates Files where regulatedSigns
Legal and tax adviceNever Provides, engaged by youInstructs
Lease or licenceSources and coordinates Solicitor reviewsSigns
Permit applicationsPrepares and lodges Authority decides after inspectionSigns, funds
Kitchen inspectionBooks, prepares, attends remotely Officer inspects in personFunds any remedial work
Extraction & fit-outSpecifies and project-manages Contractors install and certifyOwns, funds
Equipment purchaseSpecifies, sources, negotiates —Owns, funds
Hiring the head chefSources, screens, recommends —Appoints and employs
Food safety responsibilityNever Named person on the premisesAppoints them
Cooking, packing, cleaningNever Kitchen teamEmployer
Platforms, menus, reviewsPerforms, daily —Sets policy
The rule we apply

Our desk coordinates, verifies, records, communicates, monitors and reports. We do not perform anything requiring physical presence, legal authority we do not hold, or another party's licence — and in a kitchen that boundary is unusually sharp. We cannot cook, inspect, certify or carry food safety responsibility.

Get a dated stage plan for your venture

After the first consultation we issue a proposal with your stages, dependencies and every item outside our control, in writing.

Book a consultation →